Cernavoda Nuclear Power Plant

The Cernavoda Power Plant is unique in Romania and so is the security solution developed and implemented by UTI for this nationally strategic site.

The security project started in 1994 with the implementation of a security system for Unit 1. In 2001, the implemented security system was updated and improved, while a protection system for the Burnt Fuel Warehouse was implemented.

From 2004 till 2007, the physical security system developed for Unit 1 was extended and improved in view of the integration with Unit 2. This stage required complete design, installation and commissioning services for the electronic reviewing and CCTV systems.

After 2007, UTI managed the design, installation, and commissioning of the physical protection systems pertaining to the Administrative Pavilion. The year 2009 brought about design, installation and commissioning works for access control and video surveillance systems in the vital areas. The project was completed in 2011.

Besides developing new systems or updating the already installed ones, UTI also provides maintenance services for all the installed systems.

The developed works were complex, the technical solutions were designed after long hours of field analysis and part of the involved team can consider the project as a turning point in their professional formation. Moreover, the implementation of the security systems enabled the power plant to comply with all the security standards in force.