Romania Arad 172,827 116 km2

The project has been divided into two stages, the first one included 24 intersections, while the second phase was made up of 11 intersections.

Components

  • Road signaling intersection design
  • Traffic lights, traffic controllers, and detectors
  • System commissioning and testing

Advantages

  • Direct communication with the maintenance teams through the traffic controller software
  • Permanently monitored intersections
  • Close to 100% traffic light availability
  • Local adaptive functionality